Condensation in a house is water vapour from bathrooms, kitchens, laundries and people meeting a surface cold enough to turn it back into water. When that happens inside a wall or a roof space, it is out of sight and next to materials that do not tolerate being wet. Part 10.8 of the ABCB Housing Provisions deals with it in three clauses: external walls, exhaust systems and roof spaces. This note sets out what each says in NCC 2022. NCC 2025 was published on 1 May 2026; the Australian Building Codes Board lists 1 May 2027 as the date its building provisions take effect in South Australia. Which edition applies to a particular application is for the relevant authority.

Earthworks underway with JCB excavator and steel framing at Gepps Cross SA 5094

Where Part 10.8 comes from, and South Australia’s position

Each of the three clauses in Part 10.8 carries a reference to a corresponding NCC 2019 clause: 10.8.1 to 3.8.7.2, 10.8.2 to 3.8.7.3 and 10.8.3 to 3.8.7.4. Whether a particular requirement below, such as a flow rate or a run-on timer, was already in NCC 2019 is not set out in this note.

The index of South Australia’s variations to the Housing Provisions, in Schedule 8, lists Parts 4.2, 9.2, 10.2 and 13.1 and the referenced documents. Part 10.8 is not among them. South Australia also varies NCC Volume Two separately; that schedule is not covered here.

Two of the three clauses turn on climate zone. The ABCB publishes the climate zone map the NCC uses. This note does not state a zone for any South Australian location; for a particular site it is read from the map and confirmed with the certifier.

External walls: 10.8.1

Where a pliable building membrane — the wrap fixed over a wall frame — is installed in an external wall, clause 10.8.1(1) requires it to "comply with AS 4200.1", "be installed in accordance with AS 4200.2", and "be located on the exterior side of the primary insulation layer of wall assemblies that form the external envelope of a building."

Clause 10.8.1(2) then sets how readily material outside the insulation must let vapour through. A membrane, sarking-type material or insulation layer on the exterior side of the primary insulation layer must have a vapour permeance of not less than "in climate zones 4 and 5, 0.143 µg/N.s" and "in climate zones 6, 7 and 8, 1.14 µg/N.s." The explanatory information says Class 3 and Class 4 vapour control membranes, as defined in clause 5.3.4 of AS 4200.1, meet the first figure, and Class 4 membranes meet the second. It also notes that "many foil-faced insulation products have a low vapour permeance."

Clause 10.8.1(3) covers walls without a membrane: "Except for single skin masonry or single skin concrete, where a pliable building membrane is not installed in an external wall, the primary water control layer must be separated from water sensitive materials by a drained cavity."

Exhaust systems: 10.8.2

Clause 10.8.2(1) sets minimum flow rates for an exhaust system installed in these rooms: "25 L/s for a bathroom or sanitary compartment" and "40 L/s for a kitchen or laundry." Subclause (2) says where the air goes: exhaust from "a kitchen, kitchen range hood, bathroom, sanitary compartment or laundry must discharge directly or via a shaft or duct to outdoor air." Subclause (3) applies the same to a venting clothes dryer. The explanatory information notes that this does not apply to other types of dryer, "such as condensing clothes dryers".

Subclause (4) applies to a bathroom or sanitary compartment that is not ventilated under 10.6.2(a) — that is, by openings, windows, doors or other devices that can be opened, with a ventilating area of not less than 5% of the room’s floor area, opening to one of the spaces that clause lists. There, an exhaust system that is not run continuously must "be interlocked with the room’s light switch" and "include a run-on timer so that the exhaust system continues to operate for 10 minutes after the light switch is turned off."

Subclause (5) requires make-up air for a room with an exhaust system under (1) that is not ventilated under 10.6.2(a): "via openings to an adjacent room with a free area of 14,000 mm²" or in accordance with AS 1668.2. The explanatory information gives a worked example: an opening with that free area can be achieved by a 20 mm undercut to a 700 mm wide door. Subclause (6) requires make-up air in accordance with AS 1668.2 for a room with a venting clothes dryer under (3), again except for rooms ventilated under 10.6.2(a).

Roof spaces: 10.8.3

Clause 10.8.3 applies "in climate zones 6, 7 and 8". In those zones a roof must have a roof space located immediately above the primary insulation layer (or immediately above sarking of a stated vapour permeance, or immediately above ceiling insulation meeting 13.2.3(3) and (4)), with "a height of not less than 20 mm", and either ventilated to outdoor air "through evenly distributed openings in accordance with Table 10.8.3" or located immediately under the tiles of an unsarked tiled roof.

Table 10.8.3 sets the openings by roof pitch, per metre of the roof’s longest horizontal dimension. For a pitch of 15° or more and less than 75°, it is "7,000 mm²/m provided at the eaves and 5,000 mm²/m at high level", with a further 18,000 mm²/m at the eaves for a cathedral ceiling. The clause does not apply to a concrete roof, a roof made of structural insulated panels, or a roof subject to Bushfire Attack Level FZ requirements under AS 3959.

Whether 10.8.3 applies to a given house in South Australia depends on the climate zone of the site, which this note does not state.

Where these decisions are made

Most of Part 10.8 is out of sight in a finished house: the wall wrap is behind the cladding and the ducts are above the ceiling. Each is a product choice or a routing decision that belongs in the drawings and specification, where the membrane’s class, the fan’s flow rate and the duct’s end point can be stated and checked against the clause before the frame is closed in.

Common Questions

Is condensation management new in NCC 2022?

Part 10.8 did not start from nothing: each of its clauses in the NCC 2022 Housing Provisions carries a reference to a corresponding NCC 2019 clause (3.8.7.2, 3.8.7.3 and 3.8.7.4). Whether a particular requirement was already in NCC 2019 is not set out here.

Does South Australia vary Part 10.8?

The index of South Australia’s variations to the Housing Provisions in Schedule 8 lists Parts 4.2, 9.2, 10.2 and 13.1 and the referenced documents. Part 10.8 is not among them. South Australia’s separate variations to NCC Volume Two are not covered here.

What flow rate does a bathroom exhaust fan need?

Clause 10.8.2(1) sets a minimum of 25 L/s for a bathroom or sanitary compartment and 40 L/s for a kitchen or laundry. The exhaust must discharge directly, or via a shaft or duct, to outdoor air.

When does a bathroom fan need a run-on timer?

Under clause 10.8.2(4), where the bathroom or sanitary compartment is not naturally ventilated in accordance with 10.6.2(a) and the exhaust does not run continuously. The fan must then be interlocked with the light switch and run for 10 minutes after the light is turned off.

Which climate zone is my block in?

The NCC uses a climate zone map published by the ABCB. This note does not state a zone for any location; for a particular site, it is read from the map and confirmed with the certifier.

Sources

This page describes legislation as it stood on the access dates above. It is not legal advice about any particular property.

Planning a rebuild or new build in Adelaide? Start with a free initial consultation.

Want more certainty before you commit? Start with the right questions.