Pre-start meeting and selections for a new SA house

What “pre-start” means for a homeowner, how prestart selections relate to the contract and variations, and what South Australia’s consumer sources say to check before work begins

Published

In this note, ‘pre-start’ means a meeting between the owner and the builder before site work begins, to review the selections (colours, finishes, fixtures and fittings) against the drawings, specification and contract; the sources reviewed do not prescribe its agenda. What the sources do set out is how selections, prime cost items and variations sit within a domestic building contract, and Consumer and Business Services’ Form 1 puts it plainly: “Not checking now could be very expensive.” Where this note quotes the National Construction Code, it quotes NCC 2022; the ABCB lists South Australia’s NCC 2025 adoption as “BCA: 1 May 2027” and “PCA: 1 May 2026”.

Two people at a table with a laptop showing a floor plan and material samples

What does “pre-start” mean on a new home build?

The phrase is used in two different senses. On a construction site, a pre-start meeting can be a safety briefing for workers. Safe Work Australia’s model Code of Practice: Construction Work (November 2024) states: “Toolbox talks or pre-start meetings can be used by both the builder and subcontractors to provide information to and receive feedback from workers as well as assist in raising the awareness of how construction work can be carried out in a safe and healthy manner.” That meeting is about work health and safety on the site.

The second sense, and the one this note covers, is the homeowner’s pre-start: a meeting or series of appointments before the build begins in which the selections are confirmed and the contract documents are checked. The sources read for this note do not prescribe its agenda. They do say what the contract should contain and what happens when it changes.

What should be settled before work starts?

Consumer and Business Services’ consumer guide (January 2025) states that “The contract will usually contain a number of documents, including the drawings and specifications.” Form 1 is the notice that, in its own words, an owner “must be given” together with “a copy of the signed contract”. It states: “Most importantly, check to see that the work you want your building work contractor to do has been fully and accurately set out in the contract (including the plans and specifications). Do not rely on verbal promises or agreement.”

The consumer guide adds: “You should be aware that it can be costly to change specifications or requirements later – you should make sure you are happy with all details of the plans and specifications before you sign.”

One way to do that is checking the selections against the drawings and specification line by line: what is listed, what is shown on the plans, and what is still undecided. Anything that is still open at pre-start is a candidate for a later change.

How do prestart selections relate to the building contract?

The consumer guide describes a building schedule: “A building schedule details the items you have selected for your home. A provisional sum schedule states monetary allowances for the fittings or fixtures you have selected.”

On a lump sum contract, the guide says the price “also lists items as being prime-costed or estimated which means prices that can go up or down according to the item’s price at the time of purchase. The term may also allow for the price to vary according to agreed changes, for example, an additional row of built in cupboards wanted.”

Form 1 explains prime cost items: “if the standard of goods you select is higher than that provided for by your building work contractor, then you may have to pay an additional cost over and above that provided for, plus a surcharge, which may be up to 15 per cent of the cost of the item.” It notes that items designated “prime cost” or “provisional sums” “may also lead to a change in the total sum you can be charged.” The note on what a building contract must include covers these allowances in more detail.

This note quotes the September 2024 version of Form 1; the version prescribed under the Building Work Contractors Regulations 2026 was not reviewed.

What happens if you change a selection after signing?

Form 1 states: “If you want to change the work to be done at a later stage, you will have to reach agreement with your building work contractor, and your contractor will usually be entitled to make a separate, additional charge as a variation to your contract.” Its note on price adds: “Most variations require your written approval in advance, but others may be unforeseen. You should refer to your particular contract.”

The consumer guide states: “Variations to the contract should be agreed to by both parties, put in writing and signed (unless the contract allows for variations without your consent). The terms of the contract will set out whether the contract can be varied.” It adds that “All variations should be signed by you and the builder (unless the contract allows for variations without your consent) and should be attached to your original contract.”

The Law Handbook (Legal Services Commission of South Australia) says that under a lump sum contract, where the contract states a price, “Variations sought by the owner must be agreed in writing”. In its section on contract variations it says: “A building owner should read the contract carefully to find out how the contract might be varied.” It continues: “Usually the contract can only be varied if both parties agree in writing, although minor changes may occur without the owners consent.” The Law Handbook advises owners to read the variation terms and states that a building work contract “cannot purport to exclude the effect of the Building Work Contractors Act 1995 (SA)”. Legal advice is the place for a specific contract question.

Can a colour or finish selection affect compliance or approvals?

Some selections are not only a matter of taste. In the national text of the NCC 2022 Housing Provisions, clause 13.2.3(10) states: “In climate zones 1 to 5, the solar absorptance of the upper surface of a roof must not be more than 0.64.” Solar absorptance depends on the roof colour and material.

That clause sits in a Deemed-to-Satisfy Part, and clause 13.2.1(3) states that “Part 13.2 must be applied as directed in H6D2(1)(a) or (b).” A house can also meet the energy efficiency Performance Requirements by another route, and South Australia’s energy provisions must also be checked against the applicable MBS 007; this note has not verified its current text, and the relevant authority assessing the building work should confirm the provisions applicable to the application. South Australia’s Schedule 8 to the Housing Provisions varies Part 13.1, Scope and application of Section 13. Whether a change of roof colour, glazing or insulation after the energy assessment matters for a particular house is a question for the energy assessor and the relevant authority assessing the building work.

Similarly, where a selection changes something shown on the approved plans, such as an external material, whether anything further is needed under the planning and building approvals is for the relevant authority or council for that address to confirm.

What paperwork should you keep from the pre-start?

The consumer guide’s checklist says to “Keep copies of all documents – e.g. quotes, contracts, building plans, insurance, receipts and email correspondence.” On signing, it says that “Both you and the builder should initial each page and any variations or additions.”

For selections, the useful record is the final, signed version of the selections list or building schedule, alongside the drawings and specification it belongs to. If a later choice changes it, the CBS guide says variations “should be attached to your original contract”, and notes that “Changes can affect the price and extend the time of the contract”.

Who to ask before signing off selections

Questions about what a selection includes, and whether it fits the drawings, go to the builder and the designer. Questions about what the contract allows go to the contract itself and, where needed, to a lawyer or Consumer and Business Services, which Form 1 names as sources of advice. Questions about approvals go to the relevant authority or council for the address.

The consumer guide also notes that an owner “can engage an independent building consultant to carry out inspections at key stages in the building process on your behalf”, and that “it’s best to discuss this with your builder.”

Common Questions

What is a pre-start meeting for a new home?

In this note, ‘pre-start’ means a meeting between the owner and the builder before site work on a new SA house, to review the selections against the drawings, specification and contract; the sources reviewed do not prescribe its agenda. The term is also used on construction sites for a safety briefing: Safe Work Australia’s model Code of Practice: Construction Work (November 2024) says “Toolbox talks or pre-start meetings can be used by both the builder and subcontractors to provide information to and receive feedback from workers”.

What are prestart selections?

Prestart selections are the colours, finishes, fixtures and fittings chosen for a new home before building work starts. South Australia’s Consumer and Business Services consumer guide (January 2025) states: “A building schedule details the items you have selected for your home. A provisional sum schedule states monetary allowances for the fittings or fixtures you have selected.” Where a selection is a prime cost item, Form 1 (September 2024 version) says that if the goods selected are of a higher standard than allowed for, the owner may have to pay the additional cost plus a surcharge of up to 15 per cent of the cost of the item.

Can I change my colour selections after signing a building contract in SA?

CBS Form 1 (September 2024), item 4, addresses changing ‘the work to be done’; check the agreed plans, specifications and selection allowances to establish what the proposed choice would change. Form 1 states that to change the work later “you will have to reach agreement with your building work contractor, and your contractor will usually be entitled to make a separate, additional charge as a variation to your contract.” The CBS consumer guide says variations “should be agreed to by both parties, put in writing and signed (unless the contract allows for variations without your consent)”. The Law Handbook advises owners to read the variation terms and states that a building work contract “cannot purport to exclude the effect of the Building Work Contractors Act 1995 (SA)”.

Does roof colour matter for NCC compliance?

Roof colour can matter. In the national text of the NCC 2022 Housing Provisions, clause 13.2.3(10) states that “In climate zones 1 to 5, the solar absorptance of the upper surface of a roof must not be more than 0.64.” That is a Deemed-to-Satisfy provision applied as directed in H6D2; other compliance routes exist. South Australia’s energy provisions must also be checked against the applicable MBS 007; this note has not verified its current text, and the relevant authority assessing the building work should confirm the provisions applicable to the application.

Do building variations in SA have to be in writing?

The Law Handbook (Legal Services Commission of South Australia) says that under a lump sum contract, where the contract states a price, “Variations sought by the owner must be agreed in writing”, and in its section on contract variations that “Usually the contract can only be varied if both parties agree in writing, although minor changes may occur without the owners consent.” The CBS consumer guide says variations “should be agreed to by both parties, put in writing and signed (unless the contract allows for variations without your consent)”. The Law Handbook advises owners to read the variation terms and states that a building work contract “cannot purport to exclude the effect of the Building Work Contractors Act 1995 (SA)”.

Sources

This page describes these sources as they stood on the access dates above. It is not legal advice about any particular property.