Building sealing is the part of the NCC energy efficiency provisions that deals with air leaking into and out of a house through gaps around doors, windows, junctions and penetrations. In the NCC 2022 Housing Provisions it sits in Part 13.4, a Deemed-to-Satisfy Part that lists seals for external doors and windows, ceilings, walls and floors, chimneys and flues, roof lights, exhaust fans and evaporative coolers. Part 13.4 does not contain an air-tightness test; Volume Two has a separate Verification Method, H6V3, that measures air permeability at 50 Pa. This note quotes NCC 2022. The ABCB records that NCC 2025 was published on 1 May 2026, and lists South Australia as “BCA: 1 May 2027” and “PCA: 1 May 2026”. Which edition applies to a particular application is for the relevant authority assessing the building work to confirm.

What does building sealing mean in the NCC?
Clause 13.1.1 of the Housing Provisions lists six energy efficiency Parts: building fabric (13.2), external glazing (13.3), building sealing (13.4), ceiling fans (13.5), whole-of-home energy usage (13.6) and services (13.7). Part 13.4 is the one that deals with air leakage.
Clause 13.4.1(1) states that the Part applies to “a Class 1 building; and a Class 10a building with a conditioned space.” In the national text, clause 13.4.1(2) states that (1) does not apply to “A building in climate zones 1, 2, 3 and 5 where the only means of air-conditioning is by using an evaporative cooler” and to “A permanent building ventilation opening that is necessary for the safe operation of a gas appliance.” Clause 13.4.1(3) states: “Part 13.4 must be applied as directed in H6D2(1)(a) or (b).”
The explanatory information adds: “An evaporatively cooled building in climate zones 4 and 6 must be sealed because of the likelihood of the building being heated during colder periods”, and “Appropriate ventilation requirements for gas appliances can be obtained from relevant legislation, referenced standards and product installation manuals.” The ABCB page also shows a New South Wales version of 13.4.1 with different exceptions; this note quotes the national text.
Which rooms have to be sealed, and does climate zone matter?
Most of the Part 13.4 clauses apply when an element serves “a conditioned space; or a habitable room in climate zones 4, 5, 6, 7 and 8.” For Volume Two, the Glossary defines a conditioned space as “a space within a building that is heated or cooled by the building’s domestic services, excluding a non-habitable room in which a heater with a capacity of not more than 1.2 kW or 4.3 MJ/hour is installed.”
A habitable room is defined as “A room used for normal domestic activities”, which includes bedrooms, living rooms, kitchens, dining rooms, studies, family rooms and sunrooms, and excludes bathrooms, laundries, water closets, pantries, walk-in wardrobes, corridors, hallways and similar spaces.
Table 3 of the NCC 2022 Glossary lists Adelaide as climate zone 5 and Lobethal, in the Adelaide Hills, as climate zone 6; the zone for a particular address is confirmed for that address, as set out in the climate zone note.
The explanatory information to the roof light clause adds a general point for colder zones: “A roof light should be sealed regardless of which room it serves in climate zones 4, 5, 6, 7 and 8. For example, a roof light located in a hallway should be sealed to stop the transfer of cold air into adjoining conditioned spaces. This principle also applies to external doors and windows, exhaust fans, wall and floor junctions and evaporative coolers.”
How must external doors and windows be draught sealed?
Clause 13.4.4(1) states that “An external door, internal door between a Class 1 building and an unconditioned Class 10a building, openable window and other such opening must be sealed when serving— a conditioned space; or a habitable room in climate zones 4, 5, 6, 7 and 8.”
Clause 13.4.4(2) describes the seal: “for the bottom edge of a door, must be a draft protection device”, and “for the other edges of a door or the edges of an openable window or other such opening, may be a foam or rubber compressible strip, fibrous seal or the like.”
Clause 13.4.4(3) adds: “A window complying with the maximum air infiltration rates specified in AS 2047 need not comply with (2)(b).” This note does not reproduce AS 2047.
What about gaps at ceilings, walls, floors and penetrations?
Clause 13.4.6(1) states that ceilings, walls, floors and any opening such as a window frame, door frame or roof light frame “must be constructed to minimise air leakage in accordance with (2) when forming part of the external fabric of— a conditioned space; or a habitable room in climate zones 4, 5, 6, 7 and 8.”
Clause 13.4.6(2) gives two ways: construction “enclosed by internal lining systems that are close fitting at ceiling, wall and floor junctions”, or “sealed at junctions and penetrations with— close-fitting architrave, skirting or cornice; or expanding foam, rubber compressive strip, caulking or the like.”
The explanatory information states that a close-fitting internal lining system “is considered suitable to include an allowance for minimum lining movement gaps at wall, floor and ceiling junctions”, that “Caulking includes sealant, mastic or other gap filling material”, and that in 13.4.6(2)(b) “penetrations include windows, doors, roof lights, flues, exhaust fans, heating and cooling ductwork and the like.”
What sealing provisions cover chimneys, roof lights, exhaust fans and evaporative coolers?
Chimneys and flues: clause 13.4.2 states that “The chimney or flue of an open solid-fuel burning appliance must be provided with a damper or flap that can be closed to seal the chimney or flue.” The explanatory information says the requirements are to be read with the fire safety requirements in Part 12.4, and that “This clause does not apply to gas and liquid fuel burning appliances.”
Roof lights: clause 13.4.3(1) requires a roof light serving a conditioned space, or a habitable room in climate zones 4 to 8, to be “sealed, or capable of being sealed”. Under 13.4.3(2) that is done with “an imperforate ceiling diffuser or the like installed at the ceiling or internal lining level”, “a weatherproof seal”, or “a shutter system readily operated either manually, mechanically or electronically by the occupant.”
Exhaust fans: clause 13.4.5 requires an exhaust fan serving a conditioned space, or a habitable room in climate zones 4 to 8, to be “fitted with a sealing device such as a self-closing damper, filter or the like”. The exhaust fan note covers this clause alongside the ventilation rules.
Evaporative coolers: clause 13.4.7 states that “An evaporative cooler must be fitted with a self-closing damper or the like when serving— a heated space; or a habitable room in climate zones 4, 5, 6, 7 or 8.” The explanatory information adds: “The self-closing damper should create an effective seal against air infiltration.” Clause 13.4.1(2) separately excludes a building in climate zones 1, 2, 3 and 5 “where the only means of air-conditioning is by using an evaporative cooler.”
Is there an air-tightness test (blower door test) for a new house?
Part 13.4, the Deemed-to-Satisfy Part for building sealing, does not itself contain a test; its clauses describe seals, dampers and construction at junctions and penetrations. H6V2(3)(t) makes verification using H6V3 a condition of using the intended building air change rate at 50 Pa divided by 20, together with specifying that rate and additional sealing provisions beyond Part 13.4.
Volume Two contains Verification Method H6V3, “Verification of building envelope sealing”. H6V3(1) states: “Compliance with H6P1 is verified for building envelope sealing when a building envelope is sealed at an air permeability of not more than 10 m3/hr.m2 at 50 Pa reference pressure when tested in accordance with AS/NZS ISO 9972 Method 1.” The explanatory information states: “The intent is that 10 m3/hr.m2 at 50 Pa is broadly equivalent to 10 air changes per hour at 50 Pa when applied to homes.”
H6V3(2) adds conditions where “an air permeability of not more than 5 m3/hr.m2 at 50 Pa reference pressure is achieved”. H6V3(2)(a) requires a manually overridable mechanical ventilation system supplying outdoor air continuously, or intermittently with controls enabling operation for at least 25% of each four-hour segment; its minimum flow-rate formula also accounts for the fraction of each segment during which the system operates. H6V3(2)(b) requires any space with a solid-fuel burning combustion appliance to be ventilated with permanent openings directly to outside “with a free area of not less than half of the cross-sectional area of the appliance’s flue”.
Where H6V3(2) applies, H6V3(2)(c) requires ventilation of any space with a gas-fuelled combustion appliance in accordance with clauses 6.4 and 6.4.5 of AS/NZS 5601.1; H6V3(3) specifies that the space volume is considered to be 1 m³ when determining those ventilation requirements.
H6V1 states that the Verification Methods in Part H6 apply only to “a Class 1 building” and “an enclosed Class 10a building attached to a Class 1 building.” Clause A2G2(2)(b)(i) lists the Verification Methods provided in the NCC among the Assessment Methods for a Performance Solution. H6V2, the reference building method, requires building sealing to comply with “Part 13.4 of the ABCB Housing Provisions or H6V3”, and lets the calculation use “the intended building air change rate at 50 Pa, divided by 20” only where that rate and additional sealing provisions are specified “and building sealing is verified using H6V3.”
Does building sealing still apply on the 7 star (software) route?
Volume Two clause H6D2(1) gives two Deemed-to-Satisfy routes for thermal performance under H6P1: (a) “complying with S42C2, using house energy rating software and S42C4(1)”; or (b) complying with Parts 13.2, 13.3, 13.4 and 13.5 of the Housing Provisions. Part 13.4 is listed in route (b) “for building sealing”.
In the NCC 2022 text, clause S42C4(1) states that “in addition to S42C2, a building must comply with Section 13 of the ABCB Housing Provisions clauses”, and its last item is “Part 13.4, for building sealing.” South Australia’s energy provisions must also be checked against the applicable MBS 007; this note has not verified its current text, and the relevant authority assessing the building work should confirm the provisions applicable to the application. South Australian dates and concessions are discussed in the 7 star note.
H6D1(2) states that where a Performance Solution is proposed, the relevant Performance Requirements are determined in accordance with A2G2(3) and A2G4(3) as applicable. Clause A2G1(2) allows the Performance Requirements to be satisfied by a Performance Solution, a Deemed-to-Satisfy Solution, or a combination of the two.
The South Australian schedules to the Housing Provisions and Volume Two contain no variation to Part 13.4 or H6V3. SA 13.1.2(2) states that, for Section 13, “a sunroom or the like is deemed to be a Class 10a building and must comply with 13.2.7.”
Who confirms the sealing details for a new house?
Door seals, window specifications, roof light and exhaust fan details, and the way linings and junctions are finished are recorded in the drawings and specification. Whether a house meets Part 13.4, relies on H6V3, or uses another Performance Solution is for the relevant authority assessing the building work to confirm.
Building sealing interacts with ventilation and condensation, which have their own provisions and are covered in separate notes.
Common Questions
What are the building sealing requirements in the NCC?
In NCC 2022, building sealing for houses is in Part 13.4 of the ABCB Housing Provisions, which applies to a Class 1 building and a Class 10a building with a conditioned space, except for the evaporative cooler and gas appliance ventilation cases listed in clause 13.4.1(2) of the national text. It covers dampers on the chimney or flue of an open solid-fuel burning appliance (13.4.2), roof lights (13.4.3), seals on external doors and openable windows (13.4.4), sealing devices on exhaust fans (13.4.5), construction of ceilings, walls and floors to minimise air leakage (13.4.6), and self-closing dampers on evaporative coolers (13.4.7).
Is an air-tightness or blower door test required for a new house under NCC 2022?
Part 13.4 of the NCC 2022 Housing Provisions, the Deemed-to-Satisfy Part for building sealing, does not contain a test. NCC 2022 Volume Two has a Verification Method, H6V3, under which building envelope sealing is verified at an air permeability of not more than 10 m3/hr.m2 at 50 Pa when tested in accordance with AS/NZS ISO 9972 Method 1, with extra ventilation conditions where 5 m3/hr.m2 or less is achieved. South Australia’s energy provisions must also be checked against the applicable MBS 007; this note has not verified its current text, and the relevant authority assessing the building work should confirm the provisions applicable to the application. Which method a particular house relies on is for the relevant authority assessing the building work to confirm.
Does the bottom of an external door need a draught seal under NCC 2022?
Clause 13.4.4(2)(a) of the NCC 2022 Housing Provisions states that a seal to restrict air infiltration “for the bottom edge of a door, must be a draft protection device”. Under 13.4.4(1) this applies to an external door, and to an internal door between a Class 1 building and an unconditioned Class 10a building, when the door serves a conditioned space or a habitable room in climate zones 4, 5, 6, 7 and 8. Within the NCC 2022 Deemed-to-Satisfy provisions, 13.4.4(1) covers those doors when serving a conditioned space or a habitable room in climate zones 4–8, subject to 13.4.1(2), including its exclusion for buildings in climate zones 1, 2, 3 and 5 whose only means of air-conditioning is an evaporative cooler. A Performance Solution is the other way to meet the Performance Requirements.
Does building sealing apply if the house uses the 7 star NatHERS route?
In the NCC 2022 text, H6D2(1)(a) requires compliance with S42C2 using house energy rating software and with S42C4(1), and S42C4(1) lists “Part 13.4, for building sealing” among the Housing Provisions clauses a building must also meet. South Australia’s energy provisions must also be checked against the applicable MBS 007; this note has not verified its current text, and the relevant authority assessing the building work should confirm the provisions applicable to the application.
Does a house in Adelaide with only an evaporative cooler need building sealing?
In the national text of the NCC 2022 Housing Provisions, clause 13.4.1(2)(a) states that Part 13.4 does not apply to “A building in climate zones 1, 2, 3 and 5 where the only means of air-conditioning is by using an evaporative cooler.” Table 3 of the NCC 2022 Glossary lists Adelaide as climate zone 5, but the zone depends on the address. The relevant authority assessing the building work confirms how the exception applies to a particular house.
Sources
- NCC 2022, ABCB Housing Provisions — Part 13.4 Building sealing (clauses 13.4.1 to 13.4.7)Accessed 2026-11-23
- NCC 2022, ABCB Housing Provisions — Part 13.1 Scope and application of Section 13 (13.1.1, 13.1.2)Accessed 2026-11-23
- NCC 2022, ABCB Housing Provisions — Schedule 1 Definitions, Glossary (conditioned space, habitable room, climate zone and Table 3)Accessed 2026-11-23
- NCC 2022 Volume Two — Part H6 Energy efficiency (H6P1, H6V1, H6V2, H6V3, H6D1, H6D2)Accessed 2026-11-23
- NCC 2022 Volume Two — Specification 42 House energy rating software (S42C4)Accessed 2026-11-23
- NCC 2022 Volume Two — Part A2 Compliance with the NCC (A2G1, A2G2)Accessed 2026-11-23
- NCC 2022, ABCB Housing Provisions — Schedule 8 South Australia, SA 13.1.2Accessed 2026-11-23
- NCC 2022 Volume Two — Schedule 8 South Australia (index of variations)Accessed 2026-11-23
- ABCB — NCC 2025 state and territory adoption informationAccessed 2026-11-23
This page describes these sources as they stood on the access dates above. It is not legal advice about any particular property.
Planning a rebuild or new build in Adelaide? Start with a free initial consultation.