NBN lead-in conduit for a new house

What nbn’s current standard says about the lead-in conduit for a single house on an existing street: size, depth, bends, the internal conduit, power and pre-installation

Published

The nbn lead-in conduit is the pipe nbn’s New Developments standard requires from the front property boundary to the outside wall, so nbn can run its fibre in. nbn defines it as “the individual telecommunications conduit installed underground from the development boundary to the dwelling’s external telecommunications point.” Its current standard for single dwelling units, NBN-DES-STD-0011 Revision 17.0 (8 September 2026), specifies a nominal P20 white PVC-U telecommunications conduit with a minimum depth of cover of 300 mm, a maximum of 500 mm and a minimum of 450 mm under a driveway. This note covers a single house facing an existing street, not estate pit-and-pipe networks, and quotes nbn’s own documents. It does not cover fees.

Grey utility boxes with cables mounted on an exterior wall above grass

What is an nbn lead-in conduit and when is one required?

nbn’s design and build guidelines list three ways a development connects: lead-in conduits, pit and pipe, and pathways. Lead-in conduits are “Conduits connected to the nbn network directly from the front boundary of the property”. nbn’s design and build guidelines describe lead-in conduits as typically used for developments with 1 to 8 premises facing an existing road, no private roads, and no additional services requiring an nbn connection, such as fire alarms, security systems or elevator phone lines. The examples given are “Single storey house, duplexes, subdivided homes.”

Section 5 of NBN-DES-STD-0011 states: “nbn requires a LIC to be provided to each premises.” It must be installed “from (and connected to) the nbn® service drop conduit at the property boundary (if available)” and run “to the building entry at the nominated location where the PCD or NTD will be located externally on the premises.” For FTTP, nbn’s 2024 pre-installation guide places the utility box (PCD) outside and the connection box (NTD) inside; section 6 of Rev 17.0 also describes an external NTD for FTTN connections.

The standard’s objective (clause 1.2) notes that its requirements “have been provided for new developments, where the developer has an agreement with nbn to provide broadband to the premises within the new development”, and that “Developers, building owners and builders must adhere to these requirements to ensure a smooth connection of nbn® services to the premises.”

nbn’s New Developments FAQ lists the types of application to which its developer contribution charge applies. The first listed is “new dwellings or lots being constructed (e.g. houses, apartments, townhouses, villa units)”; the list also includes “where a single dwelling is built on a vacant block in a brownfield area and there is no existing nbn connection” and “knock-down rebuilds where a single house is knocked down and more than one premises is rebuilt in its place”. The FAQ states: “The charge is determined on application”. The list does not separately address a knockdown rebuild of one house replaced by one house.

Whether a particular address needs a New Developments application and a new lead-in is for nbn to confirm.

What size is the nbn lead-in conduit?

Table 3 of NBN-DES-STD-0011 Rev 17.0 sets the type for a single dwelling unit as “nominal P20 (23mm ID; 26.6mm to 26.8mm OD) white PVC-U telecommunications conduit, compliant with AS/NZS 1477 PVC pipes and fittings for pressure applications.”

nbn’s 2024 pre-installation guide says to “Install rigid white P20 telecommunications conduit (23mm internal diameter) and connect it to the service drop conduit with solvent cement, as per the manufacturer’s specifications.” Its diagram notes that “Orange or corrugated conduit must not be used”.

For duplexes and triplexes, section 5 states that “the LIC must have clear access from the property boundary directly to the PCD or NTD location for each dwelling. A LIC cannot traverse a neighbour’s property.”

How deep does the nbn lead-in conduit go, including under a driveway?

Table 3 of NBN-DES-STD-0011 Rev 17.0 sets the “Minimum depth of cover below finished ground level: 300mm” and “Maximum depth of cover below finished ground level: 500mm”, and adds: “Increase minimum depth of cover to 450mm for any service drop conduits planned to pass under a driveway.”

The table also requires that “all excavation work performed as part of installing the LIC shall be backfilled with suitable fill, compacted and reinstated to match the surrounding area.”

nbn’s 2024 pre-installation guide gives the same figures measured “From the top of the conduit to the finished surface”, and adds: “The telecommunications conduit should maintain a 300mm distance from other utility services underground. Depending on the utility, there may be shorter distances.” The 300 mm separation is a figure that does not appear in Rev 17.0. The guide says the service drop conduit from the street pit is “typically one metre inside the property boundary.”

How many bends can the conduit have, and does it need a drawstring?

Table 3 of NBN-DES-STD-0011 Rev 17.0 sets the bend limits as “Minimum radius: 300mm underground and 100mm above ground”, “Maximum individual bend angle: 90 degrees” and “Maximum total (cumulative) bend angles: 270 degrees (this is taken from the pit to the LIC end at the PCD/NTD location)”.

The drawstring is to be “Installed in the P20 LIC from the street network pit and exiting at the premises end.” Under “Seals”, the table says to “Temporarily seal at premises end during construction activity to avoid debris entering and blocking the conduit.”

The 2024 pre-installation guide says to “Rod and rope the conduit with drawstring and secure at both ends with tape”, and that “The conduit should terminate no less than 410mm from ground level”.

Where does the nbn box go on the wall, and what is needed inside?

Table 4 of the standard sets PCD clearances, including “Ground to bottom of PCD 400mm minimum”, “Heater or air conditioning unit 500mm minimum” and 500 mm from enclosed or unenclosed gas meters. Section 6 adds: “nbn® devices should not be placed directly below electrical switchboards.”

Section 6.5 requires “an internal conduit to be installed with drawstring from the external PCD/NTD location to the equipment location internally”, also nominal P20, with an FTTP spacing of “100mm - 140mm separation between the LIC and the internal conduit”, a minimum bend radius of 100 mm and joints “All glued with conduit solvent cement and primer.”

For the equipment inside, section 7 requires “a mains power outlet (GPO) This must be a dedicated socket for the exclusive use of nbn® PSU.” Clause 7.4.1 of NBN-DES-STD-0011 Rev 17.0 requires an accessible NTD location within arm’s reach without tools or a ladder, as well as a minimum height of 300 mm from finished floor level to the base of the NTD or enclosure and a maximum of 2.4 m to the top of the NTD; nbn’s preferred height is below 1.8 m. Section 3 asks that equipment positions and pathways be planned “as part of the overall building design.”

On data cabling through the house, section 9 states: “Customer cabling within premises is not within the scope of the nbn”, that such work “is subject to ACMA requirements”, and that it “remains optional and is at the discretion of the developer, builder or premises owner.” nbn’s lead-in conduit page says in-home cabling “must be done by registered cablers using our guidelines.”

What is nbn pre-installation and when is it requested?

nbn describes pre-installation as “the installation of the nbn connection box and nbn® fibre cable in an eligible property”, with fibre “extended from the street into a home while it’s still being built.” Its pre-installation page says a request “can then be made during the ‘Frame’ stage”, and the installation “will occur between completion of ‘Lock up’ stage and commencement of ‘Fit-out’ stage.”

Clause 10.1.1 of the standard lists the prerequisites: “builder has completed all preparatory installation work”, “electrical power is available” and “building is at lock-up stage”. Under clause 10.1.3, nbn installs the PCD, NTD and power supply, runs fibre from the street pit through the service drop conduit, and checks the system up to the NTD; it states that “nbn does not verify that the internal customer wiring is correctly installed.”

The 2024 pre-installation guide states that a premises is eligible “when it is a house or a townhouse and is part of an nbn New Development stage”, the address can be served by fibre to the premises, and the lead-in and internal conduit meet nbn’s specifications. nbn’s FAQ says a lot owner “can initiate a pre-installation request by providing the details of their builder.”

Who checks the nbn preparation on a new house?

nbn’s lead-in conduit page lists service-plan submission and trench preparation among the applicant’s responsibilities and recommends pre-installation; it says in-home cabling may be needed, while section 9 of Rev 17.0 states that customer cabling remains optional at the discretion of the developer, builder or premises owner. The same page says nbn “needs to review the location of the Lead in Conduit (piping from the property boundary to external wall of the house) to verify the connection specifications.”

Clause 1.5 of the standard warns that, if preparations do not comply, “Developers, building owners and builders may face delays and additional costs (borne by the owner of the premises)”, and clause 5.1 states that an alternative lead-in method used by nbn “does not remove the requirement for the provision of a LIC by the Developer/builder or property owner.”

Common Questions

What size conduit does nbn require for a house lead-in?

Section 1.2 of nbn’s NBN-DES-STD-0011 Rev 17.0 states that these requirements are provided for new developments where the developer has an agreement with nbn to provide broadband to the premises. Table 3 of nbn’s standard NBN-DES-STD-0011 Rev 17.0 (Residential Preparation and Installation – Single Dwelling Units and Multi-Dwelling Units, 8 September 2026) specifies, for a single dwelling unit, “nominal P20 (23mm ID; 26.6mm to 26.8mm OD) white PVC-U telecommunications conduit, compliant with AS/NZS 1477”. nbn’s 2024 pre-installation guide also calls for rigid white P20 conduit, glued with solvent cement, and its diagram notes that orange or corrugated conduit must not be used.

How deep should the nbn lead-in conduit be?

Rev 17.0 of nbn’s NBN-DES-STD-0011 applies to new developments where the developer has an agreement with nbn (section 1.2). Table 3 of that standard sets a minimum depth of cover below finished ground level of 300 mm and a maximum of 500 mm for the lead-in conduit, and says to “Increase minimum depth of cover to 450mm for any service drop conduits planned to pass under a driveway.” nbn’s 2024 pre-installation guide measures these depths from the top of the conduit to the finished surface.

How many bends are allowed in an nbn lead-in conduit?

Rev 17.0 of nbn’s NBN-DES-STD-0011 applies to new developments where the developer has an agreement with nbn (section 1.2). Table 3 of that standard allows a maximum individual bend angle of 90 degrees and a maximum cumulative bend angle of 270 degrees, measured from the pit to the lead-in conduit end at the external box, with a minimum bend radius of 300 mm underground and 100 mm above ground. nbn’s 2024 pre-installation guide puts it as no more than three 90-degree bends.

Does the nbn conduit need a drawstring?

Rev 17.0 of nbn’s NBN-DES-STD-0011 applies to new developments where the developer has an agreement with nbn (section 1.2). Table 3 of that standard requires a drawstring “Installed in the P20 LIC from the street network pit and exiting at the premises end”, and section 6.5 requires the internal conduit to be installed with a drawstring too. nbn’s 2024 pre-installation guide says to rod and rope the conduit with drawstring and secure it at both ends with tape.

When can nbn equipment be pre-installed in a new house?

nbn’s pre-installation page says a request can be made during the frame stage and that installation occurs between completion of lock-up and the start of fit-out. Clause 10.1.1 of nbn’s standard NBN-DES-STD-0011 Rev 17.0 lists the prerequisites as the builder having completed all preparatory work, electrical power being available and the building being at lock-up stage. nbn’s 2024 guide limits eligibility to a house or townhouse that is part of an nbn New Development stage, whose address can be served by fibre to the premises, and whose lead-in and internal conduit meet nbn’s specifications as set out in the guide.

Sources

This page describes these sources as they stood on the access dates above. It is not legal advice about any particular property.